Back to drawing board for Jaguar Nickel

After metallurgical testing on an atmospheric-pressure leaching system, Jaguar Nickel (JNI-T) has concluded the process would not be economic for the lateritic nickel at its Sechol project in the Lake Izabal region of Guatemala.

Jaguar had hoped that the process, which leaches nickel from laterite using a chloride solution, would have provided a low-cost extraction method for Sechol. It operates at atmospheric pressure, rather than the high pressures used in pressure acid leaching, and Jaguar had recognized its potential to reduce capital costs by bypassing costly autoclaves.

The capital cost of the plant had been estimated at US$306 million.

The Sechol laterites, however, have a high magnesium content, which diminishes the effectiveness of the process. Jaguar will retain its patent on the process against the day it can use it on low-magnesium nickel laterites or on nickel sulphide mineralization.

Jaguar’s next step at Sechol is to evaluate a proven extraction process. The company is also drilling the laterite and expects to come up with a new resource figure in the next two months. Estimates in March 2004 gave Sechol a measured and indicated resource of 37 million tonnes grading 1.4% nickel, based on a 1% nickel cutoff grade.

Print

Be the first to comment on "Back to drawing board for Jaguar Nickel"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close