Sherwoods step-out drilling shows Minto expansion potential

Vancouver – Step-out drilling around Sherwood Coppers (SWC-V) Minto deposit in the Yukon has returned significant copper-gold mineralization in previously untested areas, as well as a high-grade gold intercept within the Minto pit.

Six of the 11 core holes tested previously unexplored areas between, beneath, and adjacent to the known Minto main and Area 2 deposits, with encouraging results.

One hole (07SWC-176), collared 100 metres east of the Minto resource perimeter, intersected 2.95% copper and 1.07 grams gold per tonne over 11.7 metres, including 6.0 metres of 3.97% copper and 1.49 grams gold in a horizon starting 292 metres below the surface. Hole 07SWC-171, outside the west perimeter of Area 2, intersected 1.03% copper and 0.75 gram gold over 19.4 metres.

And a series of holes running in a line from Area 2 north to the main deposit confirm the presence of multiple, stacked foliated and mineralized horizons throughout. Three of the four holes intersected significant copper and gold mineralization, including one hole (07SWC-178) that intersected 2.76% copper, 1.29 grams gold, and 8.7 grams silver from 150.9 metres to 160.5 metres.

The drill results pushed Sherwoods share price up 5.3%, from US$5.70 to US$6.00.

The other five drill holes were cut within the boundaries of the main deposit in order to obtain ore for metallurgical testing. Those holes equaled or exceeded grades and thicknesses from the Minto resource model. In particular, one hole (07SWC-169) intersected 1.88% copper, 2.99 grams gold, and 8.3 grams silver over 22.3 metres, including 1.1 metres grading 14.9% copper, 46.2 grams gold, and 72.7 grams silver.

The core material is now being tested to confirm previous findings that copper recoveries can be maintained at significantly coarser grind size than assumed in the feasibility study, which could allow for increased mill throughput.

The Minto Project, located 240 km north of Whitehorse, has already seen significant exploration. The primary deposit has proven and probable reserves of roughly 5.9 million tonnes, grading 2% copper, 0.8 gram per tonnes gold, and 9.1 grams silver. A mine is more than 90% complete and Sherwood expects to move it into production by mid-2007.

Minto Explorations, a Sherwood subsidiary, owns the Minto project 100%. Copper was initially discovered in the area in the early 1970s and a feasibility study was conducted in 1995, but the project was suspended in the late 1990s due to depressed metal prices. In 2005 Sherwood acquired MintoEx and immediately embarked on further exploration and mine development.

In 2006 geologists identified an extension just to the south of the main Minto deposit, which became known as Area 2. Area 2 has a measured and indicated resource estimate of 7.6 million tonnes grading 1.26% copper and 0.48 gram per tonne gold, with a 0.5% copper cutoff. This newer discovery is advancing through a pre-feasability study; Sherwood hopes to add Area 2 resources to the reserve base by mid-2007.

A second phase of drilling, scheduled to start in June, is aimed at expanding resources in Area 2 and testing a number of other prospective targets. Wide-spaced drilling in the 1970s in several of these targets, including grades of over 3% copper over at least 5 metres.

In January Sherwood struck a deal with Yukon Energy to tap into their power grid by extending a 138-kilovolt transmission line to Minto landing and adding a 35-kilovolt line to the mine site. The feasibility study was completed assuming the need for diesel generators; Sherwood estimates electrical power cost savings of about $3-4 million annually.

In addition, Sherwood has pre-sold 41,218 tonnes of copper, 42,2002 oz. gold and 467,697 oz. silver for delivery between July 2007 and August 2011, representing about 68% of payable metal sales in the first four years of production and 35% of the overall current reserve. The company has hedged a gold price of US$636.25 per oz.., US$11.51 per oz. for silver, and a declining price for copper starting at US$3.14 per lb. and reaching $2.00 per lb. by 2011.

Print

Be the first to comment on "Sherwoods step-out drilling shows Minto expansion potential"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close