Nico Feasibility Positive

A full feasibility study on the Nico gold-cobalt-bismuth deposit in the Northwest Territories has shown favourable economics, so owner Fortune Minerals (FT-T) is planning production in 2010.

The study, by Micon International and Met-Chem Canada, estimated a mine producing 24,000 oz. gold and about 1,500 tonnes each of cobalt and bismuth would have a capital cost of $215 million. Cash production costs (treating gold and bismuth as byproducts) would average US$7.05 per lb. of cobalt.

Nico, about 160 km northwest of Yellowknife, near the Snare River hydroelectric project, would be mined as an open pit and from underground via a ramp, already partly driven to allow bulk sampling. The study puts the deposit’s proven and probable reserves at 20.6 million tonnes grading 0.85 gram gold, 0.16% bismuth and 0.13% cobalt in the proposed open pit, plus 1.2 million tonnes, grading 5.1 grams gold, 0.19% bismuth and 0.14% cobalt, in the underground mine plan.

The project would require an all-weather road, but Fortune has bought the mill from the closed Golden Giant gold mine in north-central Ontario.

The operation would mill 4,000 tonnes per day producing a sulphide concentrate that would be separated into bismuth and cobalt concentrates. The bismuth concentrate would be fed to a cyanide-leach circuit to extract the gold before drying and shipping, while the cobalt concentrate would be pressure-leached to produce cobalt in solution for electrowinning. Cobalt process tailings would also be fed to the gold plant.

At the planned production rate the operation has a life of 15 years.

The study assumed base prices for the metals equal to the average price for the past two years: US$525 per oz. for gold, US$16.50 per lb. for cobalt and US$4.50 per lb. for bismuth. It also assumed a Canadian dollar at US84.

Discounted cash flow analyses put the net present value of the project at $91.8 million, based on an 8% discount rate. The internal rate of return was just over 15%.

Fortune has a bulk sample awaiting transportation over the winter road to the Territorial highway system; it will be used for pilot-plant testing. Another bulk sample is planned for 2007, and Fortune has started work toward an environmental assessment and permitting.

Print

Be the first to comment on "Nico Feasibility Positive"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close