Rio Tinto (NYSE:RIO; LSE: RIO; ASX: RIO) unveiled on Wednesday that underground production from the Oyu Tolgoi copper-gold mine in Mongolia is slated to begin in October 2022, adding that it will come with a price tag of US$6.75 billion.
When it was approved in 2015, Rio Tinto expected the expansion to cost US$5.3 billion and reach first sustainable production in early of 2021.
In 2019, however, the company flagged stability risks associated with the original project design, which translated into as much as an additional US$1.9 billion cost. Expected production was then updated to between October 2022 and July 2023.
While both investment required and timeline for the mine expansion disclosed today were better than most analyst estimates, the world’s No.2 miner failed to provide straightforward information on its dealings with the Mongolian government.
The announcement also lacked clarity around the ongoing legal spat with its subsidiary Turquoise Hill Resources (TSX: TRQ; NYSE: TRQ), which launched in November arbitration proceedings against the mining giant to get clarity on the terms of its financing.
Rio Tinto is at odds with Turquoise Hill on how to cover a US$3 billion funding gap. It wants to use a mixture of debt, equity and reprofiling of loans, while the Canadian miner favours a package that does not include a sale of new shares.
Minority investors in Turquoise Hill, including U.S. hedge fund Pentwater Capital, oppose Rio Tinto’s attempts to force the Vancouver-based miner to conduct an equity raise.
They claim there are “much cheaper and more advantageous financing options” available to the company, such as streaming and bond financing.
They also worry about Rio Tinto growing its stake in Turquoise Hill through such an equity raising. Investors based this argument on the expectation that Rio would underwrite any shortfall created by minority Turquoise Hill shareholders who do not participate in the raising.
Analysts said the lingering issues meant the funding and economics surrounding the expansion project were not yet clear.
“It is encouraging that capex and the timeline for the project is on track, although no reasons are given for the government approval delays and the funding comment appears to offer limited new insight,” Berenberg consultants wrote in a note to investors.
RBC’s Tyler Broda said Rio Tinto’s assertion that “all of the shareholders should contribute proportionately and share equitably in the benefit” suggests the company believes to be “responsible for 100% but only shares in 33% of the economics of the project.”
Broda also highlighted that the Mongolian government has yet to approve Rio Tinto’s updated feasibility study for the expansion, published in July 2020, which is another area of uncertainty.
The analyst the outstanding issues would eventually be resolved, and that Oyu Tolgoi would account for 21% of Rio Tinto’s earnings in 2028.
Rio Tinto will also have to face the results of an independent review of the cost blowout and overrun, requested by the Mongolian government in November.
Mongolia has complained about overruns in the past. Much of Oyu Tolgoi’s copper lies deep underground. When Rio Tinto finally kicked off the delayed project, profits from surface extraction were meant to pay for digging up more of the copper below.
With time, it became clear the underground mine alone would cost much more than the original budget.
Mounting investor activism is just one of the may headaches Rio Tinto has had while building what would rank as one of the world’s three largest copper mines when operating at full capacity – now expected to be by 2025 at the earliest.
The Mongolian government’s insistence on owning an equity stake in the mine has also been a major obstacle for Rio to overcome.
A group of legislators recommended last year a review of the 2009 deal that launched construction of the mine. It also advised revoking a 2015 agreement allowing for the now ongoing underground expansion.
The parliament ended up approving a resolution in December 2019, which reconfirmed the validity of all the Oyu Tolgoi mine-related agreements. The decision brought an 18-month-long review to a close.
Mongolia has also been pondering a potential option to swap its 34% stake in the project for either royalty payments or a production sharing agreement. Under its current deal, the government won’t receive any dividends until the loans it has taken on to share its portion of the construction costs have been repaid.
Rio Tinto has repeatedly said the underground expansion is its most important growth project. Once completed, it would place Oyu Tolgoi among the top four copper mines, producing 480,000 tonnes of the metal a year from 2028 to 2036.
This article first appeared in MINING.com, part of Glacier Resource Innovation Group.
Be the first to comment on "Rio Tinto’s $6.75B Oyu Tolgoi expansion to kick off production in 2022"