Agnico-Eagle Mines moves ahead with plan to build gold mine at its Pinos Altos property in Mexico

Sean Boyd, vice chairman and chief executive of Agnico-Eagle Mines (AEM-T, AEM-N) is feeling pretty chuffed these days.

We have half a billion in cash, five mines under construction and our gold output is going to increase five times in the next three years, he says proudly.

Its an enviable spot to be in and it just got even better. New gold and silver reserve estimates at Agnico-Eagles Pinos Altos property in northern Mexico have pushed the companys plans ahead for a gold mine on the site.

Recent drilling revealed gold ounces in reserves have increased 21% and silver reserves 18% from the companys earlier estimates released in February.

Pinos Altos, 280 km west of Chihuahua, the state capital, is in the Sierra Madre gold belt, one of the most active gold and silver mining districts in the world with seven major projects and mines.

Extending from northwest to southeast through Mexico from the U.S., the rugged Sierra Madres have a great wealth of minerals including iron ore, lead, silver and gold.

Its clearly a place where there has been a lot of successful exploration so thats why we were excited about having a great asset in a great part of the world, the Toronto-based Boyd says in a telephone interview.

But its not just the rich geology that appeals to Agnico-Eagle. Low operating costs, political stability (in its first twelve months since the elections in July 2006 the new government under President Felipe Calderon has attempted to increase competition and attract foreign investment) and mining-friendly regulations, made Mexico a logical choice to help the company broaden its geographical footprint. Canadas largest gold producer also has operations in Finland and the United States. Pinos Altos will be the companys sixth gold mine.

Our geologists were very excited about the exploration potential of Pinos Altos when they first looked at it, says Boyd of the 11,000-hectare property. The geologists are bang on with their initial assessments.

Current reserves at Pinos Altos total 2.2 million oz. gold from 20 million tonnes of ore in probable reserves grading 3.5 grams per tonne, a 13% increase in gold grade over the previous reserve estimate in February. The Pinos Altos deposit also includes approximately 65.7 million oz. silver in the reserve category, an increase of approximately 10 million oz. over the previous estimate.

The February feasibility study projects an after-tax rate of return of 18.3%, based on a gold price of US$530 per oz. and a silver price of US$9.59 per oz.

Average annual production is expected to be approximately 150,000 oz. of gold at average total cash costs per ounce of US$240, including royalties and net of byproduct silver credits. Annual silver production is forecast to average over 2 million oz. per year.

Initial production is likely to begin in the second quarter of 2009. The company says it has all the necessary land agreements with the four local agricultural groups in the area and is currently negotiating additional surface rights with the underlying royalty holder. If those negotiations are unsuccessful, Boyd says, modifications to the proposed mine plan contained in the base case feasibility study will be implemented.

Approximately 60% of the Pinos Altos mineral resource is located in the Santo Nino zone along a regional fault zone that holds a number of other known deposits in the area. This Santo Nino zone has a thickness of up to 45 metres over a length of 2 km, and a vertical extent identified to over 750 metres. It remains open to the west and at depth.

The mine will have a conventional milling operation of 4,000 tonnes of ore per day and a heap leach operation reaching peak production rates of 2,500 tonnes of ore per day.

Agnico-Eagle says the ore is non-refractory, yielding excellent gold recoveries of greater than 95% with conventional cyanidation processing. Silver recoveries are expected to average 50%.

Overall mine-site operating costs are forecast to average US$39 per tonne, with construction capital costs of US$190 million and average sustaining capital expenditures of approximately US$3 million per year. Agnico-Eagle estimates that the project will be completely funded from existing cash and cash flows.

In March 2005, Agnico-Eagle signed an option agreement with Industrias Penoles (PE&OLES-BMV) to purchase the Pinos Altos property. It exercised that option in March 2006, paying cash and stock of about US$80 million.

Agnico-Eagle posted a US$37.8-million profit for the second quarter of 2007, up slightly from US$37.1 million in the year-earlier period. Cash provided by operating activities in the second quarter soared to US$79.8 million, up from US$49.5 million in the same quarter last year.

Print

Be the first to comment on "Agnico-Eagle Mines moves ahead with plan to build gold mine at its Pinos Altos property in Mexico"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close