Cigar Lake delay leaves uranium market in limbo

Vancouver – The global uranium market is expected to remain in limbo as it waits for the worlds leading producer Cameco (CCO-T, CCJ-N), to estimate the time line for a production startup at its flooded Cigar Lake mine in Saskatchewan.

During a conference all with analysts on February 7, senior Cameco executives said they will be unable to speculate on a possible startup date until the company details its progress in a technical report to be released at the end of March.

Meanwhile, the Saskatoon based company has asked several utilities to defer delivery from mine production by between five and seven years while it works to plug the holes which allowed 100,000 cubic metres of water to flood the mine workings last October.

Cameco spokesman Lyle Krahn described the proposed deferral as a kind of middle ground between cancelling the contracts altogether or trying to deliver sooner than required.

Analysts are keeping a close eye on the situation, because Cigar Lake was scheduled to deliver 18 million pounds of uranium annually [at full capacity], an amount that would have represented about 17% of global mine production.

Prior to the flood, production was expected to begin early next year.

However, the uncertainty surrounding such a key operation is affecting the market, raising expectations that prices will continue to rise after virtually doubling last year to the current US$75 a pound level.

There is no doubt that there is going to be upward pressure on prices, said Gene Clark, chief executive officer of TradeTeck a Denver-based publication that tracks the uranium market.

He said uranium buyers who are attempting to secure fixed price contracts are locked in a battle with suppliers who expect prices to rise and want to be paid at the market rate at the time of delivery.

As a result, a significant gap still exists between willing buyers and willing sellers, said Mr. Clark in a report.

Speaking to analysts on the February 7 conference call, Cameco chief executive officer Jerry Grandey predicted that remediation work designed to seal off the inflow will be completed by the second quarter of 2007.

However, due to the high level of market interest in the remediation process, he said the company will provide regular updates to let the public know how the drilling work is progressing.

Cameco chief operating officer Tom Gitzel said the company aims to seal the inflow and reinforce the underground tunnels by pouring concrete into the mine workings through 14 holes which are being drilled from surface.

The company will also drill a series of wider dewatering holes down to the lowest point of the mine workings. Due to their size, they are expected to take longer to drill. Once the dewatering holes are complete, submersible pumps, with the capacity to move 250 cubic metres of water per hour, will be lowered into the underground workings.

While required approvals for the dewatering holes are not yet in place, Mr. Krahn said the company plans to provide its next update on March 1. That will be followed by a technical report containing the capital cost of the remediation and potential timeline for a production startup times.

Cameco reported a profit of $40 million or 11 per share for the three months ended Dec. 31, 2006, down from a profit of $83 million or 23 in same period a year ago.

Revenue in the quarter slipped to $512 million from $522 million.

The company realized an average price of US$65.21 per pound for its uranium in the fourth quarter, compared to US$34.79 a year earlier.

Cameco took a $15 million write down related to Cigar Lake, which was flooded last April and again in October, as well as another $5 million in costs related to remediation activities at the project in the fourth quarter.

In addition to charges related to Cigar Lake, the company attributed its lower profits to lower earnings from its electricity and gold businesses.

Meanwhile in its Nuclear Market Review, TradeTeck said long term uranium demand remains strong with 15 utilities currently evaluating offers or seeking to purchase 54 million pounds of uranium oxide equivalent to be delivered between 2007 and 2020.

Print

Be the first to comment on "Cigar Lake delay leaves uranium market in limbo"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close