Copper Mountain boosts reserves, mine life at Similco

Vancouver – A revised mine plan for Copper Mountain Mining‘s (CUM-T) Similco project foresees the mine producing more copper for longer based on an increased reserve estimate for the British Columbia property.

Copper Mountain updated the Similco resource in mid-April, boosting measured and indicated tonnes by 42% and grade by 2.3% to 518.6 million tonnes grading 0.311% copper. Now the company has incorporated that resource increase into a new mine plan for the past-producing site.

Proven and probable reserves at the site, which is 15 km southwest of Princeton in southern B.C., now sit at 211.2 million tonnes averaging 0.361% copper for 1.68 billion lbs. contained copper.

Copper Mountain plans to extract that copper reserve, which lies around and underneath three historic pits that will grow into one super pit, at a rate of 35,000 tonnes per day. The operation would produce 100 million lbs. copper per year in concentrate, with gold and silver credits.

By the end of a 17-year mine life the operation will have produced 1.47 billion lbs. copper, 452,016 oz. gold, and 4.49 million oz. silver. The company says the project will create 274 permanent jobs.

According to the project’s feasibility study, which came out in mid-2008, it will cost $402 million to build the mine. Once operational the project should provide a 20.2% pretax internal rate of return (IRR) and it carries a net present value (NPV), using a 5% discount, of $263 million. Copper Mountain has not yet disclosed updated projections for capital cost, IRR, or NPV .

In October Mitsubishi Materials signed on a memorandum of understanding (MOU) to buy a 25% interest in the Similco project. The parties recently extended the MOU until the end of July while they finalize the joint venture agreement. The deal will leave Mitsubishi responsible for arranging a $250-million project loan. In exchange, the materials major will have the right to purchase all of the mine’s copper concentrate.

In the meantime, Mitsubishi is financing operations at the site through a $28.75-million line of credit; Copper Mountain has already spent the majority of that money on long-lead equipment items and continuing project activities, such as detailed engineering studies.

Copper Mountain purchased the past-producing Similco mine in 2006. Between 1927 and 1996 the three pits on site produced roughly 2 billion lbs. of copper. The deposit at Similco is an alkaline porphyry system with a strong structural component. Copper Mountain’s exploration efforts have defined new mineralization between, outside of, and beneath the three old pits.

On news of the increased Similco reserve and updated mine plan Copper Mountain gained 8¢ to close at $1.55. The company has a 52-week trading range of 31¢ to $1.60 and has 32 million shares outstanding.

Print

Be the first to comment on "Copper Mountain boosts reserves, mine life at Similco"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close