Cumberland eyes $25m for Meadowbank

Cumberland Resources (CBD-T) plans to raise up to $25 million by selling 7 million units and 1 million flow-through shares, with proceeds earmarked for the Meadowbank gold project in Nunavut.

Under a bought deal, the units are priced at $3.10 apiece. One unit comprises one share and half a warrant. A full warrant is good for one share at $3.75 per share for one year from closing. The exercise period is trimmed by three months if Cumberland’s shares average at least $4.25 per share over any 20-day period between four and eight months after closing.

The underwriting group, led by Canaccord Capital and Dundee Securities, will sell 1 million flow-through shares at $3.30 each on a best-efforts basis.

The group can boost the financing by up to 3 million units until closing, which is expected to be July 29.

As a commission, the underwriters will take home 5% of the gross proceeds generated by the financing. The group will also receive broker warrants (priced at $3.10 per share) representing 5% of the total number of units and flow-through shares sold.

Cumberland will use the proceeds to advance its Meadowbank project, 70 km north of Baker Lake, where an ongoing feasibility study is expected to wrap up later this year.

A preliminary assessment of the Meadowbank deposits suggests production of 250,000 oz. gold per year at a cash cost of US$168 per oz. over eight years. About 85% of the production would be mined from open pits.

At a gold price of US$325 per oz., the operation is expected to yield US$653 million in revenue and carry an 18.5% pretax rate of return, with a payback of 3.8 years.

Covering some 350 sq. km along a 25-km-long trend, Meadowbank comprises six closely spaced, near-surface deposits. Overall, measured and indicated resources stand at 15.5 million tonnes grading 4.66 grams gold. Another 8.9 million tonnes running 4.2 grams gold are classified as inferred.

A $10.5-million program of engineering, resource definition, exploration drilling, and environmental studies continues.

Print


 

Republish this article

Be the first to comment on "Cumberland eyes $25m for Meadowbank"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close