Great Panther commissioning Guanajuato plant (April 10, 2006)

Vancouver — Great Panther Resources (GPR-V, GPRLF-O) has started to commission the processing plant at its Guanajuato silver-gold mine complex in central Mexico.

Following three months of refurbishment, the 1,200-tonne-per-day plant is being put through its paces to bring it up to full capacity; the crushing, milling and flotation circuits are all being tested. The process is expected to run about four weeks.

The plant, under previous operators, had been run at a much-reduced capacity since the early 1990s, due to limited operating capital. Throughput had dropped to about 20% of capacity, or about 250 tonnes per day. Great Panther will bring the three ball mills on-stream one at a time, with all operating by year-end at full capacity.

Metallurgical testing will also review the optimal recovery process for the operation, while also examining the possibility of producing a silver-gold dor on-site.

The Guanajuato complex consists of the processing plant plus the Valenciana, Cata and Rayas mines situated on the central portion of the 25-km-long Veta Madre structure, first discovered in the mid-1500s. Historic production in the district is estimated at over 1 billion oz. silver and 5 million oz. gold.

Initial surface drilling by Great Panther, conducted in late 2005, intersected high-grade silver and gold in the Veta Madre, confirming past results. A second-phase program is now under way.

The company acquired the Guanajuato project in late 2005 for US$7.25 million in staged payments through to the end of 2006, to Sociedad Cooperativa Minero Metalrgica Santa Fe de Guanajuato — Mexico’s last mining co-operative. The co-operative ran the mine for the last 65 years.

Near the end of 2005, Great Panther also began production from its Topia silver-lead-zinc mine in Durango state.

Shares of the company rose about 8% on the news, closing at $1.70 per share on volume of over 900,000. Great Panther posts a market capitalization of $83 million based on its 49.1 million shares outstanding.

Print

Be the first to comment on "Great Panther commissioning Guanajuato plant (April 10, 2006)"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close