Hochschild Mining sees 300,000 oz per year potential in Chile gold project

Hochschild Mining sees 300,000 oz/y potential in Chile gold projectVolcan is located in the Atacama Region of Chile, on the Maricunga gold belt. (Image courtesy of Hochschild Mining.)

Hochschild Mining (LSE: HOC) said on Monday it has completed a reevaluation of its Volcan gold project in Chile, which it added to its portfolio in 2012 with the acquisition of Andina Minerals.

The precious metals miner kicked off the reassessment of the project’s viability and economic potential early last year, after Volcan had been dormant for a decade.

Hochschild said that in the past 18 months it has allocated time and resources to Volcan, including the creation of a Canadian subsidiary, Tiernan Gold, as the owner of the gold project.

It has also completed a revision of the resource estimate for the asset, which confirmed 463.3 million tonnes of measured and indicated resources grading 0.66 grams gold for 9.8 million oz.; and 75 million tonnes of inferred resources at 0.51 gram gold for 1.2 million oz. gold. 

“The updated (resource) and PEA confirm that Volcan is a large resource capable of generating significant annual gold production with substantial margins at today’s gold prices,” CEO Ignacio Bustamante, who will leave the company later this month, said in the statement.

Hochschild’s preliminary economic assessment detailed plans for a 22-million tonne-per-year open pit, heap leach operation with a 14-year mine life, producing an average of 332,000 oz. of gold annually for the first 10 years.

Overall, the mine would churn out 3.8 million oz. of gold during its estimated productive life, the company said.

The initial capital cost for the project has been pegged at $900 million, with life-of-mine sustaining capital of $276 million.

Hochschild said it had executed an agreement for a $15 million-financing with the sale of a 1.5% net smelter return royalty on the project to Franco-Nevada. It noted it had also engaged Canaccord Genuity to evaluate strategic options for Tiernan.

“Tiernan is now fully funded independently to carry out the next phases of project de-risking and, with gold prices remaining strong, we believe there is significant value in this project,” Bustamante said.

The executive said that Hochschild was looking at several options to unlock value, but its current focus was on the development of high-grade reserves and resources close to Inmaculada mine in Peru, the construction of its Mara Rosa operation in Brazil and the recent Royropata discovery near its Pallancata silver-gold mine in southern Peru.

Print

Be the first to comment on "Hochschild Mining sees 300,000 oz per year potential in Chile gold project"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.