Ivanhoe’s Kamoa-Kakula concentrator beating design throughput target

Ivanhoe's Kamoa-Kakula exports first copper concentrateKamoa-Kakula's Phase 1 concentrator plant, with the foundations for the Phase 2 concentrator on the left. The concentrate storage building is in the background. (Image courtesy of Ivanhoe Mines.)

Ivanhoe Mines (TSX: IVN; US-OTC: IVPAF) says that after the first phase of concentrator construction, the facility is exceeding designed throughput rates, treating 320,000 tonnes of mineralized material in the month ending September 20. Design capacity is 315,000 tonnes per month with a head grade of 6% copper.

Copper production for the month was a record 16,010 tonnes.

The company says the phase one concentrator, located in the Democratic Republic of Congo, will treat 3.8 million tonnes of ore annually. The mill treated 384,000 tonnes of ore grading 5.6% copper in September, including 141,000 tonnes grading 7.32% copper from the centre of the Kakula mine. Surface stockpiles have reached 3.66 million tonnes grading 4.73% copper.

The average floated concentrate grade was 55.7% copper, up from 48% in August. A total of 46,764 tonnes of copper has been produced in the first nine months of 2021.

The daily floated copper recovery rate was 85.1% during the month, up from 83% in August. A daily record copper recovery rate of 88.3% was achieved on September 12, and a daily floated copper production record of 721 tonnes was sets on September 15. A daily record high milling rate of 12,596 tonnes (the nameplate capacity is 10,500 tonnes per day) and a daily crushing record of 14,778 tonnes were achieved on September 27).

Looking ahead, Ivanhoe expects even better results.

Ivanhoe Mines promises zero emissions at Kamoa-Kakula

Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 million tonnes a year. (Image courtesy of Ivanhoe Mines.)

“There are a number of additional adjustments being incorporated into the phase one processing circuit, which will enable the concentrator to achieve better results in the next quarter. These adjustments, which also will be incorporated into the phase two processing circuit, should position us to achieve 2021 copper production in the upper end of our previous guidance of 80,000 to 95,000 tonnes. This gives us the confidence to raise the range to 85,000 to 95,000 tonnes,” said Kamoa Copper CEO Mark Farren.

The commissioning of an additional concentrate filter is being fast tracked in the mill. This will take advantage of copper feed grades and milling rates in excess of design. The extra filter is to be fully operational in early October. The concentrator is then expected to produce more than the design capacity of 200,000 tonnes of copper annually during  phase one operation.

Phase two construction is over 50% complete, and the immediate focus is on structural steel, mechanical, piping and platework erection and installation. The second plant will have an annual capacity of 3.8 million tonnes, matching the phase one plant.

A study is also underway for the third phase of concentrator construction. The work will address mining production capacity and costs, including expanded facilities at the Kansoko, Kamoa North, Bonanza zone, and Kakula West deposits. The optimal sizing of the phase three mill will also be decided.

The Kamoa-Kakula copper project is a joint venture of operator and 39.6% owner Ivanhoe Mines and partners Zijin Mining Group (39.6%), Crystal River Global (0.8%), and the Democratic Republic of Congo government (20%).

Print

Be the first to comment on "Ivanhoe’s Kamoa-Kakula concentrator beating design throughput target"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close