The site will be put on care and maintenance. Spending there will be kept to a minimum, with provisions for communities in the vicinity of the operation.
The suspension defers construction costs of about US$500 million. The companies were to have produced 530,000 oz. per year at the mine.
Placer Dome says that it remains confident in the project, and intends to resume construction when gold prices improve.
Be the first to comment on "Placer, CVG mothball Las Cristinas"