Progress for Marengo’s PNG copper-moly feasibility

Marengo Mining (MRN-T, MGO-A) is considering the financial merit behind a 50-million-tonne-per-year copper-molybdenum open pit mine in Papau New Guinea.

The Perth, Australia-based company, which listed on the TSX a month ago, released the details of the first phase of its feasibility study for the Yandera copper-moly project.

Marengo plans to complete the rest of the study by mid-2009, which will include capital cost estimates; the first part looked a development options.

The study looks at mining 450 million tonnes of ore at a grade of 0.48% copper equivalent over 10 years.

The project has an indicated resource of 163 million tonnes grading 0.49% copper equivalent, using a copper equivalent cutoff of 0.3% copper) and an inferred resource of 497 million tonnes grading 0.48% copper equivalent (using the same cutoff).

Ore would be processed at 25 million tonnes during the first two years, then ramped up to a long-term rate of 50 million tonnes per year.

Ore would be crushed near or in the mine before being transported by conveyor about 2.5 km to 4 km to the processing plant.

The company would use two 40-foot SAG mills with ball mills in tandem for the grind circuit, with separate copper and moly flotation circuits to extract the two concentrate streams.

The copper concentrate would be pumped to the port site in a slurry pipeline that would be laid alongside the mien access road and the major highway into the port town, Madang.

There, it will be treated in a thickener and drying facility before being stored in a covered storage shed, which could store up to 60,000 tonnes. Batches of about 30,000 tonnes to 35,000 tonnes would be shipped in cargo vessels.

Molybdenum, accounting for less than 5% of the metal production (and 30% of revenues) from the project concentrate, would be placed in shipping containers and back-loaded to the port facility. The second phase of the study will look at whether more downstream molybdenum processing could be done before shipping.

For the tailings, Marengo looked at a tailings storage facility within the Ramu valley, about 28 km from the plant site.

But the company is also considering deep sea tailings about 100 km from the plant site or a combination of both. Further studies are needed to determine if the tailings storage facility in the valley would be able to sustain the 10-year mine life.

It was estimated that the project would require up to 240 megawatts of power at maximum capacity. The national power provider as well as private power suppliers have been approached about developing either single or multiple solutions for the project.

Marengo shares were unchanged in Toronto before the Victoria Day weekend at 27 each with a trading volume of 3,000 shares.

In Australia, the stock gained 2%, closing at A27 with a volume of 348,000 shares.

Print

Be the first to comment on "Progress for Marengo’s PNG copper-moly feasibility"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close