An aerial view of the Renard diamond project, a joint venture of Stornoway Diamond and Soquem, in north-central Quebec. After releasing a positive scoping study on the project, part of the Foxtrot property, Stornoway believes Renard could one day be Quebec's first diamond mine.An aerial view of the Renard diamond project, a joint venture of Stornoway Diamond and Soquem, in north-central Quebec. After releasing a positive scoping study on the project, part of the Foxtrot property, Stornoway believes Renard could one day be Quebec's first diamond mine.

Vancouver — A positive scoping study for its Renard diamond project has boosted Stornoway Diamond’s (SWY-T, SWYDF-o) confidence that it might someday develop Quebec’s first diamond mine.

Renard is part of the large Foxtrot property in north-central Quebec. The property is a joint venture between Stornoway and the Quebec government agency Soquem.

The study estimated Renard hosts 11.6 million indicated tonnes grading 60 carats per hundred tonnes for 7 million carats, plus 7.2 million inferred tonnes grading 63 carats per hundred tonnes for 4.5 million carats. The resource is found in four kimberlite pipes, known as Renard 2, 3, 4, and 9, and two kimberlite dykes, called Lynx and Hibou.

In establishing a conceptual mine plan for Renard, the study considered a base case resource of 5.8 million carats taken from three of the project’s five kimberlite bodies. The financial model used US$123 per carat as the diamond price for stones from Renard 2 and 3; Renard 4 stones were valued at US$80 per carat.

The mine would combine an open-pit operation with open-stope underground mining to achieve a production rate of 3.500 tonnes per day or 1.3 million tonnes annually. The mill design allows for expansion to 1.8 million tonnes.

The pit would have a stripping ratio of 2.15:1. Underground, stope heights are dictated by geology and would vary from 40 to 100 metres. The first stopes in the sequence for each pipe would be backfilled with waste rock and cemented waste rock.

Capital costs are estimated at $308 million, of which $73 million is for the diamond processing plant. Operating costs are pencilled in at $50.39 per tonne, calculated as an average of open-pit and underground costs.

The mine life in the base case scenario of 5.8 million carats is six years. The project carries a pretax internal rate of return of 13.9% (11.8% after tax) and would produce life-of-mine revenue of $867 million. The pretax net present value is $52 million, at an 8% discount rate.

The study assumed that the proposed all-season road connecting Renard with the communities of Mistissini and Chibougamau will be built. The road, known as Route Monts Otish, is a Transport Quebec project with a target completion date of early 2009. If the provincial government does not, for some reason, build the road and the joint-venture partners have to foot the bill, capital expenses increase by $39.4 million. Annual maintenance and associated charges would increase the project operating costs by $4.49 per tonne.

With the preliminary economic assessment complete, Stornoway is preparing a two-year work program design to allow for a production decision. The company plans to conduct additional drilling and sampling to upgrade and expand resources, complete a social and environmental impact assessment, achieve the necessary permits, and conduct a full mine feasibility study.

The potential for expanding resources looks good. In addition to its indicated and inferred resources, the study determined Renard has the potential to host another 14 to 32 million tonnes grading anywhere from 31 to 164 carats per hundred tonnes, which, if proven, would add between 9 and 21 million carats to the Renard resource.

The potential resource was estimated based on kimberlite drill intersections in areas with insufficient data to establish a grade and using implied depths of up to 700 metres for kimberlite pipes.

Stornoway shares gained about 4 on the news to 14. The company has a 52-week trading range of 10-90 and 227 million shares issued.

Print

Be the first to comment on "Renard jumps another hurdle for Stornoway, Soquem"

Leave a comment

Your email address will not be published.


*


By continuing to browse you agree to our use of cookies. To learn more, click more information

Dear user, please be aware that we use cookies to help users navigate our website content and to help us understand how we can improve the user experience. If you have ideas for how we can improve our services, we’d love to hear from you. Click here to email us. By continuing to browse you agree to our use of cookies. Please see our Privacy & Cookie Usage Policy to learn more.

Close